Unit Price Applications
Example 1: Comprehensive Unit Price Calculation (Tile Installation)
Calculate the final bid unit price for installing one square meter of commercial grade ceramic floor tile given the following data: Material Cost is per sq meter, Waste Factor is percent, Labor Productivity is sq meters per hour for a crew. Setter makes per hour, Helper makes per hour. Equipment Cost is per sq meter. Markup is percent.
Step-by-Step Solution
0 of 5 Steps CompletedExample 2: Concrete Pour Unit Price
An estimator is building a unit price for cubic meter of structural concrete. Material: Ready-mix concrete costs delivered. A percent waste factor applies. Labor: A crew ( total per day) can place and finish cubic meters per day. Equipment: A concrete pump truck rents for per day. Markup: percent. Determine the fully loaded bid price per cubic meter.
Step-by-Step Solution
0 of 5 Steps CompletedExample 3: Rebar Tying Unit Price (Weight-Based)
Reinforcing steel is typically priced per ton. Material: per ton. Labor: ironworker crew costs per day and ties tons per day. Markup: percent. Calculate the bid unit price per ton.
Step-by-Step Solution
0 of 4 Steps CompletedExample 4: Converting Lump Sum to a Unit Price
A contractor must install linear meters of chain-link fence. Total Materials = . Total Labor = . Equipment = . Markup = percent. What is the blended unit price per linear meter?
Step-by-Step Solution
0 of 4 Steps Completed- Unit material cost must always incorporate the specific waste factor for that material before adding it to the assembly price.
- Labor costs must convert crew hourly or daily rates into a unit-based rate using productivity.
- The final markup percentage is applied to the aggregate of all direct unit costs.
- Complex assemblies can be estimated in aggregate and then divided by the primary quantity metric to find a blended unit price.