CIAP Document 102 - Theory & Concepts - Ciap Document102

A theoretical overview of the General Conditions of Contract for Private Construction in the Philippines, as detailed in CIAP Document 102.

Open the complete lesson

Retention Money Calculator

Calculate retention money (typically 10% of progress billings) held until project completion to ensure defect correction.

Calculation Result

From the progress billing of PHP 500,000, PHP 50,000 is retained, making the net payable amount PHP 450,000.
Retention=500000×0.10=PHP 50000Payable=50000050000=PHP 450000\begin{aligned} \text{Retention} &= 500000 \times 0.10 = \text{PHP } 50000 \\\\ \text{Payable} &= 500000 - 50000 = \text{PHP } 450000 \end{aligned}