Government Procurement - Theory & Concepts

Overview of RA 9184 (Government Procurement Reform Act), the bidding process, and PhilGEPS.

Open the complete lesson

RA 9184 Competitive Bidding Process

Step-by-step timeline of the standard government procurement process for infrastructure projects.

Step 1: Pre-Procurement Conference

Assess readiness, review specifications, and approve the Approved Budget for the Contract (ABC).

Step 2: Advertisement / Posting

Invitation to Bid is posted on PhilGEPS and the agency's website to ensure transparency.

Step 3: Pre-Bid Conference

Clarify issues and answer questions from prospective bidders.

Step 4: Submission & Receipt of Bids

Bidders submit Technical and Financial envelopes before the strict deadline.

Step 5: Bid Evaluation

Determine the Lowest Calculated Bid (LCB) by evaluating financial proposals.

Step 6: Post-Qualification

Verify and validate the documents of the LCB to determine the Lowest Calculated Responsive Bid (LCRB).

Step 7: Award of Contract

Issuance of the Notice of Award (NOA) and signing of the contract.