Construction Contracts - Examples & Applications - Liquidated Damages Calc

Understanding construction contracts, their essential elements, types, and validity.

Open the complete lesson

Liquidated Damages Calculator

In government infrastructure projects (RA 9184), liquidated damages are typically set at 1/10 of 1% of the cost of the unperformed portion for every day of delay. Once the cumulative amount reaches 10% of the contract amount, the procuring entity may rescind the contract.

Damages per Day (0.1%):10,000
Total Liquidated Damages:150,000
10% Maximum Threshold:1,000,000