Construction Methods And Project Management2D

Construction Equipment - Theory & Concepts

Selection, economics, and productivity of heavy construction equipment.

Open the complete lesson

Equipment Productivity Calculator

Calculate the productivity of heavy earthmoving equipment based on capacity, cycle time, and efficiency factor.

15
5 min
85%
load
Ideal Production
180.0 m³/hr
Pideal=V×60tcycleP_{\text{ideal}} = V \times \frac{60}{t_{\text{cycle}}}
Actual Production
153.0 m³/hr
Pactual=Pideal×E100P_{\text{actual}} = P_{\text{ideal}} \times \frac{E}{100}

Governing Equations

Pactual=V×(60tcycle)×(E100)P_{\text{actual}} = V \times \left( \frac{60}{t_{\text{cycle}}} \right) \times \left( \frac{E}{100} \right)
VV = Capacity (m³)tcyclet_{\text{cycle}} = Cycle Time (min)EE = Efficiency (%)