Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open the complete lesson

Interactive Forward Pass Visualizer

Learn and test your understanding of calculating early schedule dates.

Activity Durations
A: Site Prep3 days
B: Excavation5 days
C: Formwork4 days
D: Concreting2 days
Step 0 of 4: Explanation

We begin the forward pass with the start activity A (Site Prep). We assume a project start time of 0.

A: Site Prep (Duration: 3 days)?d=3?A: Site PrepB: Excavation (Duration: 5 days)?d=5?B: ExcavationC: Formwork (Duration: 4 days)?d=4?C: FormworkD: Concreting (Duration: 2 days)?d=2?D: Concreting
CPM Node Standard Layout (Forward Pass Only)

Early Start (ES) is on the left, Duration in the middle, and Early Finish (EF) is on the right.

ESDurEFID: Activity Name