Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass
Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.
Open the complete lessonInteractive Forward Pass Visualizer
Learn and test your understanding of calculating early schedule dates.
Activity Durations
A: Site Prep3 days
B: Excavation5 days
C: Formwork4 days
D: Concreting2 days
Step 0 of 4: Explanation
We begin the forward pass with the start activity A (Site Prep). We assume a project start time of 0.
CPM Node Standard Layout (Forward Pass Only)
Early Start (ES) is on the left, Duration in the middle, and Early Finish (EF) is on the right.
Related simulations
Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Outcomes MapModule 1: Introduction and Rationale - Cpm Pert Scurve Training Module Project Control WorkflowModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Network BuilderModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Backward Pass