Civil and Topographic Plans - Terrain, Alignment and Earthwork - Highway Profile Designer

Detailed interpretation of survey-based terrain, contours, profiles, vertical curves, cross-sections, stationing, and earthwork mass balance.

Open the complete lesson

Highway Station, Grade and Vertical-Curve Studio

Construct a symmetrical parabolic vertical curve, interrogate stations, and coordinate proposed grade with existing ground.

Curve type
crest
PVC
0+490 · 115.14 m
PVT
0+750 · 115.66 m
|A|
4.00%
K
65.0 m/%
Sample cut/fill rows
12 cut · 13 fill
0+0000+2000+4000+6000+8001+0001+200PVCPVIPVTzero grade · 0+6330+600 · FG 116.63 m · EG 100.41 m
Vertical alignment station table
StationEGFGGradeFG−EGInterpretation
0+000101.00104.362.20%3.36 millustrative fill
0+100110.98106.562.20%-4.42 millustrative cut
0+200109.24108.762.20%-0.48 millustrative cut
0+300112.39110.962.20%-1.43 millustrative cut
0+400112.27113.162.20%0.89 millustrative fill
0+500101.35115.352.05%14.00 millustrative fill
0+600100.41116.630.51%16.22 millustrative fill
0+700103.62116.37-1.03%12.75 millustrative fill
0+800101.50114.76-1.80%13.26 millustrative fill
0+900110.77112.96-1.80%2.19 millustrative fill
1+000121.39111.16-1.80%-10.23 millustrative cut
1+100120.08109.36-1.80%-10.72 millustrative cut
1+200123.15107.56-1.80%-15.59 millustrative cut
Selected station 0+600

FG = 116.629 m

EG = 100.412 m

grade = 0.508%

difference = 16.217 m

y = yPVC + (g₁/100)x + ((g₂−g₁)/(200L))x²

Formation width 10.0 m is shown for coordination context only; cross-slope, superelevation, widening, side slopes, and drainage are not solved here.

This studio verifies vertical-curve geometry, stationing, and profile reading. It does not select design speed, sight distance, K criteria, comfort, drainage, clearance, superelevation, or road-authority compliance.