Project Management - Theory & Concepts - Eng Mgmt Cpm

Project life cycle, WBS, scheduling with CPM/PERT, crashing, and earned value analysis.

Open the complete lesson

CPM Network Diagram

Duration: 12 days

Activity Durations

Adays
Bdays
Cdays
Ddays
Edays

ES: Earliest Start

EF: Earliest Finish

LS: Latest Start

LF: Latest Finish

SL: Slack (Float)

START
ES:0
D:3
EF:3
Activity A
LS:4
SL:4
LF:7
ES:0
D:4
EF:4
Activity B
LS:0
SL:0
LF:4
ES:3
D:2
EF:5
Activity C
LS:7
SL:4
LF:9
ES:4
D:5
EF:9
Activity D
LS:4
SL:0
LF:9
ES:9
D:3
EF:12
Activity E
LS:9
SL:0
LF:12
END