Engineering Management2D
Project Management - Theory & Concepts - Eng Mgmt Cpm
Project life cycle, WBS, scheduling with CPM/PERT, crashing, and earned value analysis.
Open the complete lessonCPM Network Diagram
Duration: 12 days
Activity Durations
Adays
Bdays
Cdays
Ddays
Edays
ES: Earliest Start
EF: Earliest Finish
LS: Latest Start
LF: Latest Finish
SL: Slack (Float)
START
ES:0
D:3
EF:3
Activity A
LS:4
SL:4
LF:7
ES:0
D:4
EF:4
Activity B
LS:0
SL:0
LF:4
ES:3
D:2
EF:5
Activity C
LS:7
SL:4
LF:9
ES:4
D:5
EF:9
Activity D
LS:4
SL:0
LF:9
ES:9
D:3
EF:12
Activity E
LS:9
SL:0
LF:12
END