Guided Workshop Activities and Integrated Project Output — Complete Worked Example

CPM, Pert, and S-Curve Training Module

This companion example follows one fictional irrigation project through every Module 6 activity. It demonstrates the participant inputs, controlled Google Sheet records, validations, CPM and PERT computations, S-Curve and Earned Value analysis, recovery screening, management reporting, and AI validation. Every simulation is placed beside the table and calculation that produces it.

Training-Use Disclaimer

All names, dates, amounts, quantities, events, graphs, calculations, and conclusions below are fictional and intended only for instruction. The visualizations are simulations and do not establish actual project status, contractual entitlement, official agency action, or an approved completion forecast.

Step-by-Step Solution

0 of 3 Steps Completed
1

Visual Output Index

VisualExample-data question answeredActivity
Activity weight and earned-contribution graphWhere is the missing physical accomplishment located?Activity 1
CPM network graphWhich paths are critical, and which activity currently controls?Activity 2A
PERT probability curveHow does the target duration change completion confidence?Activity 2A
Early/late/actual S-CurveWhen did actual progress leave the planned envelope?Activity 2B
Earned Value bar graphHow do PV, EV, and AC compare at the same cutoff?Activity 2B
Recovery-screening timelineWhat is the approximate remaining-duration effect of a second crew?Activity 3

I. Fictional Project Used Throughout the Workshop

FieldSimulated valueData classSource reference
Project IDNIA-PANG-LC3-2026BaselineProject Registry
Project titleRehabilitation and Concrete Lining of Lateral Canal LC-3BaselineContract
LocationSan Manuel, PangasinanBaselineContract
Facility typeConcrete-lined irrigation canalBaselineProgram of Work
Implementing officeNIA Pangasinan Irrigation Management OfficeBaselineContract
ContractorABC Infrastructure Builders — fictionalBaselineContract
Contract amountPHP 10,000,000.00BaselineContract and BOQ
Notice to Proceed1 June 2026BaselineNTP-LC3-2026-01
Approved duration50 working daysBaselineCPM-LC3-BASELINE
Original target completion7 August 2026BaselineContract calendar
Approved revised completionNot applicable — no approved revisionApproved revisionProject Registry
Reporting cutoffEnd of Working Day 40Analysis boundaryWorkshop dataset
Planned accomplishment at cutoff90.00 percentBaselineS-Curve baseline
Verified actual accomplishment76.00 percentActualInspection and quantity records
Current varianceNegative 14.00 percentage pointsCalculatedS-Curve worksheet

Scheduling Convention

The example uses a day-zero convention for CPM calculations. Durations are working days. Numeric working-day positions are used so the network logic can be checked independently from calendar-date conversion.


Activity 1 — Centralized Project Data Gathering and Validation

Example 1 — Project Registry and Source-Document Inventory

Establishing the Analysis Boundary

The group records the reporting cutoff before entering actual progress. Every accomplishment, constraint, photograph, equipment event, and report statement must refer to a condition on or before Working Day 40.

Completed Source-Document Inventory

Document or recordAvailabilitySimulated referenceEvidence levelData statusUse in analysis
Approved Program of WorkAvailablePOW-LC3-REV0Level 1VERScope and activity weights
Bill of QuantitiesAvailableBOQ-LC3-REV0Level 1VERQuantities and cost weights
Approved construction scheduleAvailableCPM-LC3-BASELINELevel 1VERDurations and relationships
Notice to ProceedAvailableNTP-LC3-2026-01Level 1VERSchedule origin
Daily inspection reportsAvailableDIR Day 1–40Level 2VERActual dates and conditions
Weekly accomplishment reportsAvailableWAR Week 1–8Level 2VERProgress trend
Progress photographsAvailablePhoto Folder LC3-W1-W8Level 2VERVisual support
Concrete quantity recordsAvailableCQR-01 to CQR-12Level 2VERAccepted lining quantity
Equipment utilization logsPartially availableEUL Day 1–39Level 2PENMixer and backhoe operation
Rainfall recordsAvailableRR-June-July-2026Level 2VERWeather-event review
Updated catch-up scheduleNot submittedPending contractor submissionLevel 3MISRemaining-duration forecast
Formal extension requestNot submittedNoneLevel 3NAPNo entitlement analysis

Evidence Interpretation

  • The approved schedule establishes the baseline logic and duration.
  • Inspection and accepted-quantity records establish verified physical accomplishment.
  • The incomplete equipment log supports only a limited preliminary issue statement.
  • A verbal completion prediction is not an approved revised completion date.
  • No extension recommendation can be made without the required entitlement and critical-path review.

Example 2 — Centralized Workbook Controls and Formula Checks

Workbook controlExample result
Activity ID uniquenessPASS — A through K are unique
Weight totalPASS — 100.00 percent
Invalid predecessor referencePASS — every predecessor exists
Baseline overwrite protectionPASS — baseline columns are locked
Approved-revision referencePASS — no revised date entered without approval
Data-status dropdownPASS — only VER, PEN, MIS, INC, UNS, or NAP accepted
Formula-cell protectionPASS — CPM, PERT, and S-Curve formulas are protected

Example Spreadsheet Formulas

PurposeExample formulaSimulated result
Weight total=SUM(weight_range)1.0000 or 100.00 percent
Weight quality flag=IF(ABS(SUM(weight_range)-1)<0.0001,"PASS","REVIEW")PASS
Segment 2 earned contribution=0.20*0.550.11 or 11.00 percent
PERT expected duration for excavation=(8+4*10+15)/610.50 days
PERT variance for excavation=((15-8)/6)^21.3611
Progress variance at cutoff=0.76-0.90-0.14
Standard-normal probability=NORM.S.DIST(-0.8616,TRUE)Approximately 19.45 percent

Formula Control

Participants may inspect source cells and formulas, but they must not overwrite protected formula cells. A copied value must be checked against the controlled calculation before acceptance.

Example 3 — Validated Activity, Logic, Quantity, and Weight Table

IDActivityRelationship and predecessorDurationQuantity or scopeWeightSourceStatus
AMobilizationStart3 daysOne lot4%CPM and POWVER
BSurvey and setting outFS after A4 daysFull alignment3%CPM and POWVER
CClearing and grubbingFS after B5 daysCanal work limits6%CPM and BOQVER
DCanal excavationFS after C10 days2,500 cubic metres18%CPM and BOQVER
ESubgrade preparationFS after D5 days1,000 metres8%CPM and BOQVER
FConcrete lining — Segment 1FS after E8 days500 metres20%CPM and BOQVER
GConcrete lining — Segment 2FS after E8 days500 metres20%CPM and BOQVER
HCuring and quality testingFS after F and G7 daysCompleted lining7%CPM and methodVER
IProcurement and delivery of gatesFS after A20 daysFour gates6%CPM and BOQVER
JGate installationFS after H and I5 daysFour gates5%CPM and methodVER
KFinal inspection and turnoverFS after J3 daysOne lot3%CPM and contractVER
Total100%

Logic-Validation Observations

Validation questionResultRequired action
Are all Activity IDs unique?YesNone
Do all predecessor IDs exist?YesNone
Do weights total 100 percent?YesNone
Are curing, testing, inspection, and turnover represented?YesRetain
Is procurement represented as a parallel path?YesRetain separate path
Does gate installation require civil readiness and delivered gates?YesRetain H and I as predecessors
Is segment-specific curing represented?NoRecord as a recovery review, not approved logic

Example 4 — Correct Classification of Project Information

StatementCorrect data classReason
Original completion is 7 August 2026BaselineSupported by approved records
Contractor expects completion nine days laterForecast or proposedNot an approved revision
Segment 2 is 55 percent complete at Day 40ActualSupported by accepted quantity
Add a second crew beginning tomorrowProposed corrective actionRequires implementation and review
Four rainfall-affected days occurredActual eventSupported by rainfall and inspection records
Contractor is entitled to four additional daysContractual conclusion not establishedRequires entitlement and critical-path analysis

Example 5 — Verified Actual Accomplishment and Earned Contribution

Calculating Segment 2 Contribution

Concrete Lining Segment 2 has an approved project weight of 20 percent and verified completion of 55 percent.

Earned contribution=20%×0.55=11%\text{Earned contribution}=20\%\times0.55=11\%

Segment 2 contributes 11 percentage points to total project accomplishment at the cutoff.

Completed Accomplishment Table

ActivityWeightVerified completionEarned contributionPrimary evidence
Mobilization4%100%4.00%Mobilization record
Survey and setting out3%100%3.00%Survey acceptance
Clearing and grubbing6%100%6.00%Quantity and inspection record
Canal excavation18%100%18.00%Accepted excavation quantity
Subgrade preparation8%100%8.00%Inspection record
Concrete lining — Segment 120%100%20.00%Concrete quantity and tests
Concrete lining — Segment 220%55%11.00%Accepted 275 of 500 metres
Curing and quality testing7%0%0.00%Not started under baseline logic
Gate procurement and delivery6%100%6.00%Delivery acceptance
Gate installation5%0%0.00%Not started
Final inspection and turnover3%0%0.00%Not started
Total100%76.00%

Module 6 simulated graph

Activity Weight and Earned Contribution

Compare each approved activity weight with the value earned at Working Day 40.

Fictional training data
Approved activity weights and earned contributions at Working Day 400%5%10%15%20%AMobilization4/4BSurvey and setting out3/3CClearing and grubbing6/6DCanal excavation18/18ESubgrade preparation8/8FConcrete lining — Segment 120/20GConcrete lining — Segment 211/20HCuring and quality testing0/7IGate procurement and delivery6/6JGate installation0/5KFinal inspection and turnover0/3Approved weightEarned contribution
Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.

Activity-Weight Graph Interpretation

  • The gray bar represents each activity's approved weight.
  • The colored overlay represents earned contribution at the reporting cutoff.
  • Segment 2 has earned 11 of its 20 percentage points, leaving a 9-point gap.
  • Curing and testing, gate installation, and final inspection have no earned contribution because they have not started.
  • The graph locates missing earned value; the constraint register is still required to explain the causes.

Example 6 — Constraint, Missing-Data, and Change Logs

Constraint Register

Event IDActivitySimulated eventObserved effectEvidencePreliminary responsibility status
C-01GContinuous rainfall prevented concrete placementFour lost working daysRainfall and inspection reportsPending contract review
C-02GConcrete mixer breakdownTwo days of reduced productionEquipment logContractor-controlled
C-03GInsufficient second-segment crewContinuing productivity lossManpower reportContractor-controlled
C-04GNo serviceable backup mixerRecovery riskEquipment inventoryContractor-controlled
C-05HCombined curing successor for both lining segmentsPrevents start until F and G finishApproved CPMSchedule-logic review required

Missing-Data Register

Data issueStatusEffect on analysisFollow-up ownerDue date
Equipment log for Working Day 40MISComplete downtime cannot be confirmedContractor representativeNext working day
Resource-loaded catch-up scheduleMISReliable completion forecast unavailableContractorWithin three days
Formal extension requestNAPNo entitlement review can be madeContract administratorNo action until submission
Approval for segment-specific curingPENRecovery option cannot be assumedProject EngineerWithin two days

Change Log

TimestampField changedOld valueNew valueSource and reasonEditor
Day 1, 11:10Segment 2 completion60 percent55 percentCorrected to accepted 275/500 mQuantity Lead
Day 1, 11:22Gate procurement status90 percent100 percentDelivery acceptance locatedDocumentation Lead
Day 1, 11:35Extension request statusPendingNot submittedConfirmed by Contract AdministratorProject Data Lead

Activity 1 Quality-Gate Result

The project identity, cutoff, source inventory, activity logic, weights, actual accomplishment, and constraint records are sufficiently complete for the training computation. Missing information remains a limitation and is not replaced with an assumption.


Activity 2A — CPM and PERT Schedule Analysis

Example 7 — Schedule Logic Audit Before Calculation

Intentionally Flawed Draft Relationships

ActivityFlawed predecessorProblem
H — Curing and testingF onlyOmits Segment 2 lining
J — Gate installationI onlyIgnores civil readiness and curing
K — Final inspectionKCircular self-reference
I — Gate procurementBlankDisconnected activity

Corrected Relationships

ActivityCorrected predecessorValidation basis
H — Curing and testingF and GBoth segments complete under baseline logic
J — Gate installationH and ICivil readiness and gate delivery required
K — Final inspectionJInspection follows completed installation
I — Gate procurementAProcurement begins after mobilization

Logic-Audit Lesson

A spreadsheet can calculate a mathematically valid schedule from physically invalid logic. Constructability, approval requirements, testing, procurement, and turnover logic must be checked before CPM results are accepted.

Example 8 — Forward Pass

Step-by-Step Solution

0 of 4 Steps Completed
1

Example 9 — Complete CPM Table

IDDurationESEFLSLFTotal FloatFree FloatStatus
A3030300Critical
B4373700Critical
C571271200Critical
D101222122200Critical
E52227222700Critical
F82735273500Critical
G82735273500Critical
H73542354200Critical
I2032322421919Non-critical
J54247424700Critical
K34750475000Critical

Parallel Critical Paths

ABCDEFHJKA-B-C-D-E-F-H-J-K
ABCDEGHJKA-B-C-D-E-G-H-J-K

Module 6 simulated graph

CPM Network and Current Controlling Activity

Inspect the two parallel critical branches and the non-critical gate-procurement path.

Fictional training data
CPM network for the fictional canal rehabilitation projectA3d · TF 0B4d · TF 0C5d · TF 0D10d · TF 0E5d · TF 0F8d · TF 0G8d · TF 0H7d · TF 0I20d · TF 19J5d · TF 0K3d · TF 0Critical relationshipNon-critical relationshipCurrent controlling activity

Selected

GConcrete lining — Segment 2

Baseline paths

Two critical branches

Current control

G — Segment 2 lining

Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.

CPM Network Interpretation

  • Both lining branches have zero Total Float in the baseline.
  • Gate procurement is non-critical and has 19 days of Total Float and Free Float.
  • Segment 1 is complete, while Segment 2 is only 55 percent complete.
  • Segment 2 is the current controlling activity because H requires both F and G.
  • Current control is determined from CPM logic plus actual status, not from the S-Curve alone.

Example 10 — PERT Three-Point Estimates

IDActivityOptimistic (a)Most likely (m)Pessimistic (b)Expected durationVarianceMain uncertainty
AMobilization2343.000.1111Access readiness
BSurvey3454.000.1111Control verification
CClearing4585.330.4444Site obstructions
DExcavation8101510.501.3611Rainfall and subsurface conditions
ESubgrade4575.170.2500Moisture and inspection
FLining Segment 168128.331.0000Concrete production and weather
GLining Segment 268118.170.6944Crew and equipment availability
HCuring and testing57107.170.6944Test and acceptance timing
JGate installation4585.330.4444Fit-up and lifting
KInspection and turnover2343.000.1111Punch-list closure

Excavation PERT Calculation

te=8+4(10)+156=10.50 dayst_e=\frac{8+4(10)+15}{6}=10.50\text{ days}
σ2=(1586)2=1.3611\sigma^2=\left(\frac{15-8}{6}\right)^2=1.3611

Example 11 — Deterministic-versus-PERT Path Comparison

PathActivitiesExpected durationPath varianceStandard deviation
F branchA-B-C-D-E-F-H-J-K51.83 days4.52782.13 days
G branchA-B-C-D-E-G-H-J-K51.67 days4.22222.05 days

Path Interpretation

The deterministic branches are equal at 50 days. After expected durations are applied, the F branch is slightly longer. The difference is small, so both branches remain risk-significant.

Target-Date Probabilities

Z50=5051.832.13=0.8616Z_{50}=\frac{50-51.83}{2.13}=-0.8616
P(T50)19.45%P(T\leq50)\approx19.45\%
Z55=5551.832.13=1.4882Z_{55}=\frac{55-51.83}{2.13}=1.4882
P(T55)93.17%P(T\leq55)\approx93.17\%

Module 6 simulated graph

PERT Completion-Probability Curve

Move the target duration to see the approximate probability of completion under the stated assumptions.

Fictional training data
PERT completion probability for the selected critical path444648505254565860Mean 51.83 dTarget 50 dProject duration, working days

Completion probability

19.5%

Z-score

-0.86

Model parameters

μ = 51.83 d · σ = 2.13 d

Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.

PERT Probability-Graph Interpretation

  • The amber line represents the expected project duration.
  • The movable target line represents the duration being evaluated.
  • The shaded area represents approximate completion probability at or before the target.
  • Moving the target from 50 to 55 days increases the displayed probability substantially.
  • The result is a risk estimate, not proof of entitlement or a guaranteed finish date.

Example 12 — Schedule-Risk Register

RiskAffected activity or pathSignalPotential consequenceResponseUpdate trigger
Heavy rainfallD, F, and GWide duration rangeSlower earthwork and concrete outputWeather monitoring and protected workForecast change or lost workday
Mixer failureF and GDocumented breakdownCritical lining delayBackup mixer and checksEquipment fault or low output
Insufficient crewGCurrent actual conditionRemaining quantity delayedAdditional qualified crewDaily output below target
Testing delayHPessimistic duration of 10 daysDownstream delayPrebook testing and inspection resourcesTest slot or result delay
Parallel-path switchF and GExpected durations are closeEither branch may controlMonitor both remaining durationsOne branch exceeds the other

Activity 2A Quality-Gate Result

The network is connected, forward and backward passes are consistent, both float types are shown, parallel critical paths are identified, and PERT estimates have stated sources and limitations.


Activity 2B — S-Curve and Project-Status Analysis

Example 13 — Plot-Ready Early, Late, and Actual Dataset

Reporting weekEarly-start cumulativeLate-start cumulativeActual cumulativeActual minus earlyActual minus late
Week 16.10%4.00%5.00%-1.10 points+1.00 point
Week 212.70%9.00%11.50%-1.20 points+2.50 points
Week 322.00%15.00%19.00%-3.00 points+4.00 points
Week 432.50%25.00%29.00%-3.50 points+4.00 points
Week 541.80%38.00%38.00%-3.80 points0.00 points
Week 660.00%55.00%52.00%-8.00 points-3.00 points
Week 785.00%78.00%68.00%-17.00 points-10.00 points
Week 890.00%89.40%76.00%-14.00 points-13.40 points

Module 6 simulated graph

Early, Late, and Actual S-Curve Envelope

Inspect the planned envelope, reporting-period variance, and first boundary breach.

Fictional training data
S-Curve envelope and actual progress for the fictional canal project0%20%40%60%80%100%W0W1W2W3W4W5W6W7W8First boundary breach: W6Early startLate startActual

Early plan

90.0%

Late plan

89.4%

Actual

76.0%

Variance

-14.0 / -13.4 pts

Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.

S-Curve Interpretation

  • Actual progress remains within or on the early-late envelope through Week 5.
  • Week 6 is the first period where actual progress falls below the late-start boundary.
  • At Week 8, the project is 14.00 percentage points behind the early-start plan and 13.40 points below the late-start boundary.
  • Variance improves from -17 points in Week 7 to -14 points in Week 8, but the project remains materially behind.
  • The graph identifies variance magnitude and trend; CPM identifies the controlling activity.

Current Progress Indicators

Progress Variance=76%90%=14 percentage points\text{Progress Variance}=76\%-90\%=-14\text{ percentage points}
SPI=7690=0.8444SPI=\frac{76}{90}=0.8444

SPI Limitation

The simplified SPI is a progress-screening indicator. It does not replace an updated CPM remaining-duration forecast.

Example 14 — Activity-Level Explanation of the 14-Point Variance

Source of missing earned contributionCalculationMissing contribution
Unfinished 45 percent of Segment 2 lining20 percent weight × 45 percent incomplete9 points
Curing and testing not startedFive points planned by cutoff5 points
Total explained variance14 points

Cause-and-Magnitude Discipline

The table identifies where earned contribution is missing. The constraint register identifies documented conditions affecting the activities. Neither table independently establishes contractual responsibility.

Example 15 — Optional Earned Value Extension

IndicatorValue
Budget at CompletionPHP 10,000,000
Planned ValuePHP 9,000,000
Earned ValuePHP 7,600,000
Actual CostPHP 8,200,000

Earned Value Indicators

SV=EVPV=1,400,000SV=EV-PV=-1{,}400{,}000
CV=EVAC=600,000CV=EV-AC=-600{,}000
SPI=EVPV=0.8444SPI=\frac{EV}{PV}=0.8444
CPI=EVAC=0.9268CPI=\frac{EV}{AC}=0.9268

Module 6 simulated graph

Earned Value Status at Working Day 40

Compare Planned Value, Earned Value, and Actual Cost at one consistent reporting cutoff.

Fictional training data
Earned Value indicators at Working Day 400M2M4M6M8M10MPHP 9.0MPVPlanned ValuePHP 7.6MEVEarned ValuePHP 8.2MACActual Cost

Schedule variance

-PHP 1.4M

Cost variance

-PHP 0.6M

SPI

0.844

CPI

0.927

Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.

Earned Value Graph Interpretation

  • Planned Value is highest because 90 percent of budgeted value should have been earned.
  • Earned Value is lower because only 76 percent of budgeted work has been accepted.
  • Actual Cost exceeds Earned Value, producing negative Cost Variance and CPI below 1.00.
  • The graph adds cost-efficiency context; CPM and the evidence register are still required to explain the cause.

Activity 2B Quality-Gate Result

The group has a complete plot-ready dataset, identifies the first envelope breach, reports variance precisely, connects the condition to CPM logic, and uses one reporting cutoff for the optional cost analysis.


Activity 3 — Integrated Project Output Development

Example 16 — Evidence-Linked Root-Cause Analysis

Cause or conditionEvidenceAffected activityResponsibility statusAssessed effectConfidence
Continuous rainfallRainfall and inspection recordsG — Segment 2 liningPotentially excusable, subject to contract reviewFour lost working daysEvent high; entitlement unresolved
Concrete mixer breakdownEquipment logG — Segment 2 liningContractor-controlledTwo days reduced outputHigh
Insufficient crewManpower recordsG — Segment 2 liningContractor-controlledProduction below targetHigh
No backup mixerEquipment inventoryG — Segment 2 liningContractor-controlledRecovery delayedHigh
Combined curing logicApproved baseline scheduleH — Curing and testingSchedule-planning conditionH waits for both segmentsHigh

Root-Cause Conclusion

The records do not support attributing the entire variance to rainfall. Weather, equipment, manpower, and schedule-logic conditions are all present. Responsibility and entitlement remain separate questions requiring formal review.

Example 17 — Corrective-Action Matrix

IssueRequired actionResponsible partyDeadlineExpected effectMonitoring indicatorEscalation trigger
Segment 2 is 55 percent completeDeploy an additional qualified lining crewContractorWithin 1 dayIncrease outputDaily completed metresOutput below recovery target for two days
Mixer reliabilityMobilize and test a backup mixerContractorWithin 1 dayReduce downtime riskDaily availabilityPrimary and backup unavailable
No accepted forecastSubmit resource-loaded catch-up CPMContractorWithin 3 daysEstablish forecastSchedule review statusNo acceptable submission
Weekly-only monitoringIntroduce daily critical-activity reportSite EngineerImmediatelyDetect shortfall earlyDaily quantity and resourcesMissing report or adverse trend
Rainfall effect unresolvedComplete records and contract reviewProject Engineer and Contract AdministratorWithin 5 daysSeparate delay effectsWritten assessmentRequired record remains missing
Combined curing logicReview segment-specific curing and testingTechnical reviewerWithin 2 daysDetermine valid overlapApproved or rejected methodNo decision before readiness

Example 18 — Decision Register

Decision requiredDecision ownerInformation requiredDue dateRisk of no decisionStatus
Accept or reject catch-up scheduleProject EngineerLogic, resources, calendars, remaining durationsOne day after submissionUnreliable forecastOpen
Permit segment-specific curingTechnical reviewerMethod, quality plan, contract consistencyWithin two daysLost recovery opportunity or unsafe overlapPending information
Determine weather-delay treatmentContract AdministratorRainfall, reports, path effect, clausesAfter complete reviewPremature entitlement decisionOpen
Escalate resource deficiencyProject ManagerDaily output and equipment trendOn trigger breachContinued critical delayMonitoring

Example 19 — Recovery-Scenario Screening

Screening Assumptions

Remaining Lining Duration

One crew=22525=9 working days\text{One crew}=\frac{225}{25}=9\text{ working days}
Two crews=22545=5 working days\text{Two crews}=\frac{225}{45}=5\text{ working days}

Module 6 simulated graph

Recovery-Scenario Screening Timeline

Compare the remaining-duration effect of one crew and two crews without treating either scenario as approved.

Fictional training data

The screen compares remaining work only. It does not account for approval, congestion, safety, quality, or additional cost.

Remaining-duration screening from Working Day 40Day 40Day 44Day 48Day 52Day 56Day 60Day 64Current: one crewG9dH7dJ5dK3dFinish D64Screening: two crewsG5dH7dJ5dK3dFinish D60G: Remaining liningH: Curing/testingJ: Gate installationK: Inspection

One-crew finish

Day 64

Two-crew screening

Day 60

Potential reduction

4 working days

Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.

Recovery Graph Interpretation

  • The one-crew screen reaches completion at approximately Day 64.
  • The two-crew screen reaches completion at approximately Day 60.
  • The apparent four-day reduction comes only from the changed lining-productivity assumption.
  • Curing, testing, installation, and final inspection remain downstream and sequential.
  • The graph is not an approved catch-up schedule; safety, quality, congestion, cost, resource availability, and contractual review remain necessary.

Example 20 — Management-Ready Executive Summary

Integrated Executive Summary

As of Working Day 40, the Rehabilitation and Concrete Lining of Lateral Canal LC-3 had achieved 76.00 percent verified physical accomplishment against 90.00 percent planned accomplishment, resulting in a negative variance of 14.00 percentage points. The actual S-Curve first fell below the late-start boundary in Week 6 and is currently 13.40 percentage points below that boundary. The CPM network contains two parallel baseline critical paths through Concrete Lining Segments 1 and 2. Segment 1 is complete, while Segment 2 is only 55 percent complete and presently controls the start of curing, testing, gate installation, final inspection, and turnover. Documented contributing conditions include rainfall-affected working days, concrete-mixer breakdown, insufficient crew deployment, and the absence of a backup mixer. The simplified PERT analysis indicates low confidence in the 50-day target under the stated uncertainty assumptions. Management should require an updated resource-loaded catch-up schedule, immediate crew and equipment response, daily critical-activity monitoring, and timely technical review of segment-specific curing. Any extension decision should remain reserved until weather effects, responsibility, entitlement, and critical-path impact are formally evaluated.

Analysis Limitations

  • No accepted updated CPM schedule is available.
  • Equipment records are incomplete for Working Day 40.
  • PERT uses a simplified critical-path variance approximation.
  • Correlation and repeated critical-path switching are not fully modeled.
  • The recovery screen excludes detailed safety, quality, congestion, learning, and cost effects.
  • Segment-specific curing has not been approved.
  • No formal extension request or entitlement analysis exists.

Example 21 — Peer-Review Log

Peer-review findingClassificationCorrectionStatus
Draft said “14 percent delayed”PrecisionChanged to “14 percentage points behind”Closed
Gate procurement listed as a causeCPM inconsistencyRemoved; complete with 19 days floatClosed
Recovery action lacked triggerAction qualityAdded daily-output and deadline triggersClosed
PERT probability lacked limitationRisk communicationAdded model assumptionsClosed
Extension recommendation was prematureContract governanceChanged to reserved decisionClosed

Activity 3 Quality-Gate Result

Technical values are consistent with the controlled workbook, causes are evidence-linked, actions and decisions are separated, graphs use the same reporting cutoff, limitations are disclosed, and peer-review findings are resolved.


Activity 4 — AI-Assisted Review, Drafting, and Validation

Example 22 — Structured AI Prompt

AI-Assisted Project-Status Drafting Prompt

Role: Act as a construction project-controls drafting assistant.
Verified source data: Use only the supplied project profile, controlled CPM table, PERT summary, S-Curve table, accepted accomplishment table, root-cause table, and sanitized constraint register.
Task: Draft a concise management-level project-status narrative and corrective-action table.
Output format: Return an executive summary, findings table, follow-up actions, and missing-information list.
Restrictions: Do not recalculate the schedule, invent dates or quantities, add causes, determine accomplishment, assign entitlement, approve an extension, or state a completion date as certain.
Validation instruction: Flag every missing, inconsistent, uncertain, or unsupported item separately and identify the supplied source category used for each statement.

Example 23 — Simulated Raw AI Response with Deliberate Errors

Unverified AI Draft

The following response intentionally contains plausible but unsupported statements so participants can practice validation.

Raw AI Response — Do Not Accept Without Review

The project is 14 percent delayed because rainfall and late gate delivery prevented the contractor from maintaining the schedule. Segment 2 lining is critical, and the project will finish exactly nine days late. Management should grant a ten-day extension and direct the contractor to add a second lining crew. Gate procurement should be expedited because it has no float. The project remains fully recoverable if all recommendations are implemented immediately.

Example 24 — Claim-Level AI Validation Log

AI statementStatement typeVerification sourceResultCorrected wording or action
Project is 14 percent delayedInterpretationS-Curve tableRevise14 percentage points behind planned accomplishment
Rainfall caused the delayCauseConstraint registerReviseRainfall contributed; equipment and manpower are also documented
Late gate delivery caused delayCauseCPM and delivery recordsIncorrectReject; gates delivered and Activity I has 19 days float
Segment 2 lining is criticalFactCPM tableAcceptedRetain
Project will finish exactly nine days lateForecastNo accepted catch-up scheduleUnsupportedUpdated CPM forecast required
Grant a ten-day extensionEntitlement recommendationNo entitlement analysisRejectedReserve decision pending formal review
Add a second lining crewRecommendationRecovery screenAccept with revisionSubject to safety, quality, resource, and schedule review
Gate procurement has no floatCalculationCPM tableIncorrectReplace with 19 days Total and Free Float
Project is fully recoverableForecastNo accepted recovery planMore information requiredRecovery must be demonstrated and monitored

Example 25 — Challenge Prompt

Adversarial Review Prompt

Review the draft against the verified facts. List any statement that asserts an unsupported cause, arithmetic result, completion forecast, entitlement, approval, or certainty. Do not repair the draft yet. Return the statement, problem type, and evidence needed.

Simulated Challenge Findings

Flagged statementProblem typeEvidence needed
Late gate deliveryContradicted causeDelivery record and procurement float
Exactly nine days lateUnsupported forecastUpdated remaining-duration CPM
Grant ten-day extensionUnsupported entitlementContract, responsibility, and delay analysis
No floatIncorrect calculationControlled CPM table
Fully recoverableOverconfidenceAccepted recovery plan and production trend

Challenge Review Limitation

A second AI pass may identify errors, but it does not replace human verification. The system may fail to challenge an earlier claim or introduce a different unsupported statement.

Example 26 — Corrected AI-Assisted Narrative

Validated Final Narrative

As of Working Day 40, verified physical accomplishment is 76.00 percent against 90.00 percent planned accomplishment, placing the project 14.00 percentage points behind the early-start baseline. The actual curve is also 13.40 percentage points below the late-start boundary. Concrete Lining Segment 2 is on a critical branch and currently controls the start of curing and testing. Documented contributing conditions include rainfall-affected working days, concrete-mixer breakdown, insufficient crew deployment, and the absence of a serviceable backup mixer. Gate procurement is complete and is not a current controlling cause because the activity has 19 days of Total Float and Free Float. The final completion effect and recovery potential cannot be stated with certainty until an updated resource-loaded CPM schedule is submitted and reviewed. Management should require immediate recovery planning, additional qualified resources, daily monitoring, and formal review of weather effects while reserving any extension decision pending contract and critical-path analysis.

Human Engineering-Judgment Statement

The final report was reviewed against the controlled project workbook and supporting records. AI was used only to assist with organization and drafting. All accepted statements, interpretations, and recommendations were independently checked by the designated technical reviewers, who retain responsibility for the final engineering judgment.

Activity 4 Quality-Gate Result

The prompt, supplied data, original response, challenge response, claim-level validation, corrections, and human reviewer are preserved. Unsupported AI conclusions are excluded from the report.


Final Presentation Example

Ten-Segment Presentation Outline

SegmentRequired contentSimulated key message
1. Project profileIdentity, duration, cutoff, planned and actual progressDay 40; 90 planned versus 76 actual
2. Data qualityRecords, missing data, limitationsCatch-up schedule and Day 40 equipment log missing
3. CPM graphNetwork, float, parallel paths, controlling activityTwo critical branches; G currently controls
4. PERT graphExpected duration and target confidence50-day confidence approximately 19.45 percent
5. S-Curve graphEnvelope, breach, variance, trendFirst late-boundary breach in Week 6
6. Earned Value graphPV, EV, AC, SPI, CPIBehind schedule and cost efficiency below 1.00
7. Root causesEvidence and affected activityWeather plus equipment and manpower conditions
8. Recovery graphAssumptions, screening result, limitationsPossible four-day reduction, not approved
9. AI validationMajor AI errors and correctionsGate-delay and extension claims rejected
10. Final judgmentRequired management positionRecover immediately; reserve entitlement decision

Final Engineering Conclusion

The fictional project is materially behind its approved progress baseline. The current variance is linked to incomplete Concrete Lining Segment 2, which lies on a critical branch and prevents downstream curing, testing, installation, inspection, and turnover from proceeding under the baseline logic. Immediate recovery action is required, but the available data do not support a certain completion forecast or extension entitlement. The appropriate management position is to require an updated resource-loaded catch-up schedule, enforce daily monitoring of critical work, validate weather and equipment records, review technically valid overlap opportunities, and reserve contractual decisions until responsibility and critical-path effect are established.

Facilitator Answer Key

Required questionExpected answer
Reporting cutoffEnd of Working Day 40
Weight total100 percent
Verified actual progress76.00 percent
Early-start progress varianceNegative 14.00 percentage points
First late-start boundary breachWeek 6
Deterministic critical pathsF and G parallel branches
Current controlling activityG — Concrete Lining Segment 2
Gate procurement float19 days Total and Free Float
Slightly longer PERT pathF branch at 51.83 days
Approximate 50-day probability19.45 percent under stated assumptions
Sole cause rainfall?No
Extension recommendation now?No; formal analysis incomplete
Immediate justified actionsCatch-up schedule, crew, backup mixer, daily monitoring, technical review

Complete Example Submission Checklist

Key Takeaways
  • Every graph is produced from a controlled table and one reporting cutoff.
  • The activity-weight graph locates missing earned contribution.
  • The CPM network identifies critical paths, float, and the current controlling activity.
  • The PERT curve communicates target-date confidence under explicit assumptions.
  • The S-Curve shows variance magnitude, trend, and envelope position.
  • Earned Value adds cost-efficiency context only when PV, EV, and AC are verified.
  • The recovery timeline communicates a screening result, not an approved schedule.
  • AI-generated conclusions remain unverified until checked statement by statement.
  • Final engineering judgment must remain traceable to evidence and reproducible calculations.