FW10 — Cross-Section Survey and Earthwork Quantity Determination

I — Project Details

ItemRecord
Fieldwork / ProjectFW10 — Cross-Section Survey and Earthwork Quantity Determination
LocationUniversity Campus — Assigned Alignment
Date / TimeOctober 29, 2026; 1:00–4:00 PM
Group / SectionGroup 1 / CE Surveying
AlignmentSta. 0+000 to Sta. 0+060
Station Interval20.000 m
Offsets-6, -3, 0, +3, +6 m
Vertical ReferenceBM-01 = 100.000 m
Volume MethodAverage End Area
Weather / GroundClear; dry cross-section lines

II — Survey Team and Equipment Used

A — Survey Team

MemberAssignment / DescriptionRemarks
Student AParty ChiefNone
Student BLevel / Total Station OperatorNone
Student CRod / Prism PersonNone
Student DRecorderNone
Student EStationing and Offset AssistantNone
Student FSafety ObserverNone

B — Equipment Used

Equipment / InstrumentID / DescriptionQuantityRemarks
Automatic LevelLV-021Compensator checked
Leveling RodLR-051Serviceable
Steel TapeST-04; 30 m1Used for stationing and offsets
Offset StakesStations and ± offsets20Labeled
Turning PlateTP-Plate-011Stable
PPE SetHigh-visibility vest and closed shoes6Complete

III — Project Sketch and Photo Documentation

A — Project Sketch and Cross-Section Figure

FW10 — Cross-Section and Earthwork Quantities

B — Google Maps Location Points

Point / AreaMap RecordPurpose / Limitation
Alignment limitsVerified pins for Sta. 0+000 and 0+060 required in actual reportGeographic context
Alignment routeMarked Google Maps line required in actual reportSite orientation and access
Stations and offsetsField stationing recordEngineering geometry remains authoritative

C — Photo Documentation — Dedicated Page

Reserve one complete report page for the embedded original images represented by this register.

PhotoImage FileDescription
1FW10-photo-01.jpgCenterline station and offset points established
2FW10-photo-02.jpgRod observation at a left-side offset
3FW10-photo-03.jpgCross-section line viewed normal to the alignment
4FW10-photo-04.jpgCompleted field notes showing station and offset labels

IV — Observations and Data

A — Existing Ground and Computed Formation Data

StationOffset (m)Existing Ground (m)Design Formation (m)Ground − Formation (m)Condition
0+000-6100.40099.880+0.520Cut
0+000-3100.25099.940+0.310Cut
0+0000100.100100.000+0.100Cut
0+000+3100.05099.940+0.110Cut
0+000+699.95099.880+0.070Cut
0+020-6100.10099.980+0.120Cut
0+020-3100.020100.040-0.020Fill
0+0200100.050100.100-0.050Fill
0+020+3100.120100.040+0.080Cut
0+020+6100.08099.980+0.100Cut
0+040-6100.000100.080-0.080Fill
0+040-3100.050100.140-0.090Fill
0+0400100.080100.200-0.120Fill
0+040+3100.020100.140-0.120Fill
0+040+699.960100.080-0.120Fill
0+060-6100.050100.180-0.130Fill
0+060-3100.120100.240-0.120Fill
0+0600100.180100.300-0.120Fill
0+060+3100.110100.240-0.130Fill
0+060+6100.000100.180-0.180Fill

B — Cross-Section Areas

StationCut Area (m²)Fill Area (m²)
0+0002.4450.000
0+0200.4980.138
0+0400.0001.290
0+0600.0001.575

C — Average-End-Area Volumes

IntervalLength (m)Cut Volume (m³)Fill Volume (m³)
0+000 to 0+02020.00029.4311.381
0+020 to 0+04020.0004.98114.281
0+040 to 0+06020.0000.00028.650
Total60.00034.41344.313

V — Computations and Assumptions

The centerline formation rises at +0.50%+0.50\% from 100.000 m at Sta. 0+000, with a symmetric 2.00%2.00\% crossfall:

Ef(x,o)=100.000+0.005x−0.02∣o∣E_f(x,o)=100.000+0.005x-0.02|o|

Example at Sta. 0+020, offset −6 m-6\text{ m}:

Ef=100.000+0.005(20)−0.02(6)=99.980 mE_f=100.000+0.005(20)-0.02(6)=99.980\text{ m}

At Sta. 0+020, each sign-changing strip is split at the interpolated zero crossing before cut and fill areas are summed. Cut and fill are not netted within the mixed section.

Average End Area:

V=A1+A22LV=\frac{A_1+A_2}{2}L

First-interval cut volume:

Vc=A0+000+A0+0202(20)=29.431 m3V_c=\frac{A_{0+000}+A_{0+020}}{2}(20)=29.431\text{ m}^3

Net geometric balance:

44.313−34.413=9.900 m3 fill excess44.313-34.413=9.900\text{ m}^3\text{ fill excess}

Assumptions and conventions:

  • Left offsets are negative and right offsets are positive.
  • Positive ground-minus-formation is cut; negative is fill.
  • Ground changes linearly between measured offsets for trapezoidal area computation.
  • Volumes use the Average End Area method over 20.000 m intervals.
  • No shrinkage, swell, stripping, topsoil, or unsuitable-material factor is applied.
  • Reported volumes use unrounded section areas; the area table is rounded to three decimals.
  • Existing-ground observations remain separate from computed formation elevations and quantities.

VI — Remarks and Conclusions

A — Remarks

  • The alignment transitions from predominantly cut to fill.
  • Offset stationing, rod plumbing, interpolation across irregular ground, and missed break points are probable error sources.
  • Material factors are excluded; quantities are geometric only.
  • Mixed cut/fill at Sta. 0+020 was split at zero crossings.

B — Conclusion

The calculated geometric totals are 34.413 m³ cut and 44.313 m³ fill, giving 9.900 m³ fill excess under the Average End Area method. These values do not include construction material adjustment factors.