Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Diagram Visualizer

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open the complete lesson

PERT Probabilistic Diagram Visualizer

PERT Network DiagramATe=3.0v=0.11BTe=6.3v=1.00CTe=4.0v=0.11DTe=7.5v=1.36ETe=3.2v=0.25
Critical Path
Non-Critical

Node B: Excavation

Project Totals (Critical Path)

Total Exp. Duration:20.00 d
Total Variance:2.72
Project Std Dev:1.65 d