Back to Cpm Pert And S Curve Training Module repository
Cpm Pert And S Curve Training Module2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Probability Curve

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open the complete lesson

Completion Probability Analysis

Z-Score
Z=43.040.02.0=1.50Z = \frac{43.0 - 40.0}{2.0} = 1.50
Probability
93.32%
Probability Distribution CurveTe=40Td=43