Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Risk Sensitivity

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open the complete lesson

Schedule Risk Sensitivity Analysis

Toggle specific risk events to see their impact on the overall expected duration and uncertainty of the project.

Risk-Adjusted Schedule

Expected Duration (TeT_e)
Te=38.0+0.0=38.0 daysT_e = 38.0 + 0.0 = 38.0 \text{ days}
Total Variance (VpV_p)
Vp=1.25+0.00=1.25 days2V_p = 1.25 + 0.00 = 1.25 \text{ days}^2
Standard Deviation (σp\sigma_p)
σp=1.25=1.12 days\sigma_p = \sqrt{1.25} = 1.12 \text{ days}