Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Earned Value Control

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open the complete lesson

EVM-Style Schedule & Cost Control Dashboard

Monitor Earned Value (EV), Planned Value (PV), and Actual Cost (AC) to chart project status.

Baseline Parameters

₱600,000

Budgeted value of work planned for this period.

₱540,000

Budgeted cost value of physical work actually accomplished.

₱620,000

Actual financial expenditure incurred for the completed work.

Control Quadrant Map
Cost Index (CPI)Schedule Index (SPI)Under Budget / BehindUnder Budget / AheadOver Budget / BehindOver Budget / Ahead0.51.01.50.51.01.5
Schedule Var (SV)-₱60,000
Cost Var (CV)-₱80,000
Schedule Index (SPI)0.90
Cost Index (CPI)0.87
Critical Concern (Behind Schedule & Over Budget)

Major delays and cost overruns. Action item: Immediate critical path crashing and cost audit required to salvage project baseline.