Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Progress Variance
Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.
Open the complete lessonS-Curve Progress Variance & Slippage Analyzer
Compute physical S-curve accomplishments and classify contractor schedule slippage.
Physical Quantities accomplished
Excavation & Subgrade (Weight: 30%)8,500 / 10,000 m³
0% doneAccomplishment: 85.0%
Concrete Canal Lining (Weight: 50%)1,800 / 2,500 m
0% doneAccomplishment: 72.0%
Reinforcement Steel (Weight: 20%)38,000 / 40,000 kg
0% doneAccomplishment: 95.0%
Overall Progress Status
Planned Progress88.0%
Actual Progress80.5%
SLIPPAGE (PV vs AV)-7.5%
-20%-15% (Termination)-10% (Warning)-5%0%+10%
Slippage Warning
Contractor must submit a Catch-up Program (revised schedule).
Weighted Progress Formula:
Current Computation:
Related simulations
Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Outcomes MapModule 1: Introduction and Rationale - Cpm Pert Scurve Training Module Project Control WorkflowModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Network BuilderModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass