Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Recovery Scenario

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open the complete lesson

Schedule Recovery Scenario Simulator

Explore the budget and risk trade-offs between Crashing, Fast-tracking, and taking no action.

Severe Delay (50% progress)On Schedule (100% progress)
Extra Budget Impact₱0 (No Cost)
Rework Risk Index
5%
M0M1M2M3M4M5M6M7M8M9M100%50%100%
Actual Accomplishment (Months 0-5)
Projected Forecast S-Curve
Scenario Analysis:

Option: No Action. The current delay trends project a completion delay of roughly 1 to 2 months. No budget impact, but liquidated damages may apply.